Work had to be done in stages in order to maintain the central heating throughout the building
The old boilers were close to 1000kg and had to be broken down into manageable sections to be taken down the stairs
We successfully removed and replaced both boilers with more smaller, lighter and energy efficient systems
- Location of project:
- Duration of project:
- Value of project:
- Number of Engineers:
- Scope:
- Brighton
- 15 days
- Between £120 000 and £140 000
- 5
- Boiler Replacement